Gross Peak Demand at Northern Powergrid Primary Substations DFES 2021 (System Transformation)

Northern Powergrid DFES 2021

You're previewing the first 4 rows of this file.

Download CSV Download
Primary 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2044 2045 2046 2047 2048 2049 2050 Licence area Voltage level Scenario name Output parameter
ACKLAM 17.3 17.253 16.849 16.425 16.119 15.963 15.95 16.174 16.469 16.837 17.277 17.804 18.518 19.204 20.006 20.904 21.843 22.79 23.933 24.986 25.982 26.847 27.764 28.411 28.843 29.224 29.57 29.991 30.241 30.483 30.678 30.831 NPgN Primary NG FES - System Transformation (EE CF) Total peak demand (MW)
AMBERTON ROAD 23.196 23.111 23.108 22.73 22.443 22.29 22.263 22.513 22.878 23.314 23.821 24.418 25.306 26.135 27.09 28.155 29.287 30.583 31.985 33.265 34.439 35.47 36.581 37.304 37.819 38.251 38.644 39.151 39.432 39.697 39.915 40.086 NPgN Primary NG FES - System Transformation (EE CF) Total peak demand (MW)
ANNFIELD 66/20KV 20.766 20.709 20.316 19.91 19.605 19.44 19.41 19.627 19.947 20.346 20.826 21.4 22.221 23.052 24.02 25.102 26.247 27.464 28.921 30.262 31.5 32.582 33.717 34.507 35.068 35.553 36 36.545 36.867 37.176 37.438 37.653 NPgN Primary NG FES - System Transformation (EE CF) Total peak demand (MW)
ASHINGTON 18.566 18.553 18.204 17.844 17.593 17.487 17.52 17.794 18.154 18.596 19.12 19.743 20.597 21.456 22.455 23.57 24.75 25.972 27.441 28.794 30.044 31.136 32.266 33.08 33.656 34.153 34.613 35.155 35.492 35.815 36.095 36.334 NPgN Primary NG FES - System Transformation (EE CF) Total peak demand (MW)