Primary 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2044 2045 2046 2047 2048 2049 2050 Licence area Voltage level Scenario name Output parameter
ACKLAM 88 102 105 145 188 235 283 365 449 539 640 754 922 1031 1165 1327 1517 1711 2053 2381 2701 3005 3399 3677 3955 4228 4491 4814 5038 5238 5409 5550 NPgN Primary NG FES - System Transformation (EE CF) Number of heat pumps (total)
AMBERTON ROAD 129 153 155 204 253 305 357 448 540 638 745 865 1042 1167 1318 1498 1708 1924 2323 2706 3068 3414 3856 4174 4491 4804 5107 5474 5733 5968 6176 6355 NPgN Primary NG FES - System Transformation (EE CF) Number of heat pumps (total)
ANNFIELD 66/20KV 93 111 113 147 180 216 253 320 392 469 556 654 797 912 1053 1221 1418 1618 2012 2393 2759 3107 3544 3861 4180 4494 4800 5170 5430 5666 5878 6064 NPgN Primary NG FES - System Transformation (EE CF) Number of heat pumps (total)
ASHINGTON 98 117 120 165 212 262 313 402 492 588 694 814 991 1120 1279 1467 1687 1910 2339 2753 3151 3530 4010 4356 4704 5046 5378 5779 6060 6316 6545 6745 NPgN Primary NG FES - System Transformation (EE CF) Number of heat pumps (total)