Gross Peak Demand at Northern Powergrid Primary Substations DFES 2021 (Customer Transformation)

Northern Powergrid DFES 2021

You're previewing the first 4 rows of this file.

Download CSV Download
Primary 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2044 2045 2046 2047 2048 2049 2050 Licence area Voltage level Scenario name Output parameter
ACKLAM 17.2 17.198 16.671 15.827 15.504 15.545 15.72 16.025 16.449 17.01 17.706 18.658 19.896 21.188 22.459 23.709 24.885 26.387 27.584 28.672 29.65 30.563 31.467 32.113 32.616 32.984 33.268 33.49 33.673 33.839 33.982 34.096 NPgN Primary NG FES - Consumer Transformation (EE CF) Total peak demand (MW)
AMBERTON ROAD 23.13 23.032 22.939 22.168 21.838 21.844 21.975 22.31 22.748 23.309 23.994 24.856 26.131 27.387 28.642 29.876 31.073 32.538 33.655 34.663 35.547 36.331 37.053 37.532 37.902 38.171 38.367 38.518 38.651 38.77 38.871 38.948 NPgN Primary NG FES - Consumer Transformation (EE CF) Total peak demand (MW)
ANNFIELD 66/20KV 20.717 20.649 20.151 19.354 19.032 19.061 19.217 19.54 19.98 20.551 21.254 22.163 23.423 24.718 26.007 27.262 28.457 29.896 31.027 32.051 32.946 33.756 34.522 35.049 35.459 35.768 36.023 36.217 36.363 36.493 36.6 36.683 NPgN Primary NG FES - Consumer Transformation (EE CF) Total peak demand (MW)
ASHINGTON 18.523 18.5 18.037 17.276 17.006 17.088 17.306 17.673 18.158 18.776 19.529 20.493 21.774 23.106 24.435 25.736 26.98 28.453 29.635 30.704 31.643 32.496 33.304 33.876 34.329 34.667 34.915 35.116 35.296 35.456 35.59 35.698 NPgN Primary NG FES - Consumer Transformation (EE CF) Total peak demand (MW)