| HMRC_0030_2122-Q1 |
Borders & Trade Programme |
HMRC |
Government Transformation and Service Delivery |
Post-Brexit, the repatriation of powers from the European Union afforded the UK a significant opportunity to transform how we operate our borders over the medium and longer term to deliver lasting economic benefits.
To prepare for the end of the Transition Period on 31 December 2020, several key changes were successfully delivered to ensure a functioning border. However, the late conclusion of the Trade and Cooperation agreement and the pandemic had significant impacts on traders' readiness for border controls and customs procedures. This resulted in the introduction of multiple easements to enable trade at the border to continue to flow.
The Programme set out critical activity HMRC needed to deliver in 2021-2022 to achieve stabilisation of border activity, understand and implement the roll-back of easements and fully operationalise a secure Border whilst establishing a stable and sustainable foundation from which to advance our medium to longer term aims. |
Green |
|
The Infrastructure Project Authority's Delivery Confidence Assessment rating at 21/22-Q4 is Green The main strategic objective to implement full border controls was achieved through delivery of Ending of Staged Customs Controls on 01 January 22 (excluding Safety & Security declaration requirements for imports - to be implemented in line with the timeline presented in the corresponding Government announcement). Alongside this, critical work has continued to support the Northern Ireland Protocol requirements and ongoing negotiations with the European Union. The Programme also successfully delivered the building blocks by ensuring HMRC has a stable operating model upon which to build the future strategic customs platform by supporting the stabilisation and resilience of the IT platform and delivery of an effective, sustainable and affordable operating model.
HMRC restructured to effectively deliver the 2021 Spending Review settlement and the longer-term border strategy. The Programme has started formal closure and, as part of this, risks and issues will close or transfer to the new programme structure. |
2021-04-01 |
2022-03-31 |
Your project end-date is 31 MAR 2022. This is primarily due to the following factors: The programme funding was linked the 2020 Spending Review one-year funding settlement; the three-year 2021 Spending Review settlement, covering 2022-25, enabled HMRC to position itself for delivery of the longer- term border strategy. The Programme completed on 31st March 2022, and separate successor programmes will take forward the 2021 Spending Review change delivery. Formal programme closure is being progressed with appropriate oversight from the Infrastructure & Projects Authority. |
£410.20 |
£379.12 |
-8% |
The budget variance exceeds 5%. The main areas contributing to the 21/22 underspend are;
. Grant payments due to insufficient demand for the support available to small and medium sized businesses to adjust to new Customs, Rules of Origin, and VAT rules when trading with the European Union; and
. Spend on border IT systems due to scope and design changes as a result of policy changes. |
£410 |
Your projects Baseline Whole Life Cost is 410.20 (£m). This is primarily due to the following factors: The Programme Baseline Whole Life Cost is £410.2m. The whole life cost was revised and updated in November 2022 and consisted of customs grants; increased certainty around IT and resource costs; and items being de-scoped. The Programme only obtained funding for 2021/22 and will therefore be formally be closed on 31 March 2022. |
| HMRC_0015_1617-Q1 |
Building Our Future Locations Programme |
HMRC |
Government Transformation and Service Delivery |
HMRC's Locations Strategy, announced in 2015, is key to enabling its wider transformation. The Locations Strategy is delivering the Phase One Government Hubs and supports the Government's Places for Growth Programme by creating opportunities and career paths in towns and cities across the UK.
Going forward HMRC will be operating from a network of large modern regional centres and specialist sites and a Head Office in Westminster. Our new buildings are environmentally efficient and provide flexible, fully inclusive workspaces supporting smarter working and meeting future changing demands and priorities of use. |
Green |
|
Compared to financial year 20/21-Q4, the Infrastructure Project Authority's Delivery Confidence Assessment rating at 21/22-Q4 decreased from Amber to Green The Programme has successfully delivered 9 Regional Centres, alongside a hub at Canary Wharf.
During Financial Year 2021/22, Regional Centres were delivered in Liverpool and Birmingham, and the Programme is on track to deliver a further 3 during Q1 of 2022/23.
Following approval from the Chief Secretary to the Treasury (CST), the Programme announced that Portsmouth will become our 14th Regional Centre and East Kilbride will be the location for the second phase of Glasgow Regional Centre.
The agreement for lease for the Newcastle Regional Centre was signed in November 2021. |
2016-01-05 |
2026-03-31 |
Compared to 2021-Q4, your project end-date remained scheduled to finish on 31 MAR 2026 . This is primarily due to the following factors: The Programme remains on target to complete on 31st March 2026 |
£231.70 |
£270.05 |
16% |
The budget variance exceeds 5%. The 2021/22 full year final position at Q4 is 16% higher than baseline, this is primarily because of the following factors:
HMRC re-prioritisation of its programme Portfolio resulting in deferral of expenditure for several projects into 2021/2022
Civil Service Compensation Scheme terms not changing as originally expected resulting in exits remaining more expensive |
£2,836 |
Compared to 2021-Q4,the projects Baseline Whole Life Cost remained at 2835.90 (£m). This is primarily due to the following factors: The baseline Whole Life Cost as at Q4 2021/22 is unchanged from £2,835.90m reported in the 2020/21 report. It has not been formally updated since the Programme Business Case v1.0 was approved by HMT in April 2017. |
| HMRC_0029_2122-Q3 |
Data Protection Remediation Programme |
HMRC |
Government Transformation and Service Delivery |
The Programme (DPRP) will deliver remediation activity to ensure HMRC regulatory compliance linked to its legal obligations under General Data Protection Regulation (GDPR) and the Data Protection Act 2018 (DPA 2018). |
Amber |
|
The Infrastructure Project Authority's Delivery Confidence Assessment rating at 21/22-Q4 is Amber Actions being taken to move the programme towards Green include agreeing a multi-year plan for the remaining scope and securing long term funding to deliver this. |
2021-04-01 |
2025-03-31 |
Your project end-date is 31 MAR 2025. This is primarily due to the following factors: The programme is currently on track and expects to complete by 31st March 2025. |
£30.00 |
£12.94 |
-57% |
The variance is mainly due to some planned activity not being required or removed from the scope of the programme, supplier costs being overestimated, and the revision of the programme plan to move some work into the next financial year. |
£205 |
Your projects Baseline Whole Life Cost is 205.00 (£m). This is primarily due to the following factors: Whole life costs represent IT costs and resource costs. |