2016 - 2026

Northern Powergrid 10 year investment plan

You're previewing the first 4 rows of this file.

Download CSV Download
Title Technical Description Area Of Work Value Start Date Duration Connected Customers OS Grid Ref 1 OS Grid Ref 2
Beeston Royds to Gildersome Condition data has suggested that 2.2km of these 33 kiloVolt underground cables are in need of replacement. Underground Cable Replacement 1,011,508.20 2024 1 year 5878 SE2414728300 SE2749931203
Beeston Royds to Kirkstall Condition data has suggested that 3.1km of these 33 kiloVolt underground cables are in need of replacement. Underground Cable Replacement 1,367,527.62 2023 1 year N/A SE2715734571 SE2749931203
Ferrybridge to Whinmoor Condition data has suggested that 1.2km of these 132 kiloVolt underground cables are in need of replacement. Underground Cable Replacement 956,838.24 2022 1 year 46539 SE3568837650 SE4821624964
Leeds East to Knostrop Condition data has suggested that 1.3km of these 33 kiloVolt underground cables are in need of replacement. Underground Cable Replacement 484,064.01 2019 1 year 2 SE3335631835 SE3240634042